ExamSIDE
Questions (Powered by ExamGOAL)
Industrial Engineering
QueuingProduction Planning and ControlLine BalancingForecastingLinear ProgrammingAssignmentPert and CpmInventory ControlTransportationScheduling
Scheduling
Practice Questions
Marks 1
1

A set of jobs $U, V, W, X, Y, Z$ arrive at time $t = 0$ to a production line consisting of two workstations in series. Each job must be processed by both workstations in sequence (i.e., the first followed by the second). The process times (in minutes) for each job on each workstation in the production line are given below.

JobUVWXYZ
Workstation 1573468
Workstation 2466857

The sequence in which the jobs must be processed by the production line if the total makespan of production is to be minimized is

GATE ME 2024
Marks 2
1

Parts P1 - P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is _______ hours.

Part

Milling (hours)

Polishing (hours)

P1

8

6

P2

3

2

P3

3

4

P4

4

6

P5

5

7

P6

6

4

P7

2

1

GATE ME 2022 Set 2
2
Following data refers to the jobs $$(P, Q, R, S)$$ which have arrived at a machine for scheduling. The shortest possible average flow time is ___________ days. GATE ME 2017 Set 1 Industrial Engineering - Scheduling Question 6 English
GATE ME 2017 Set 1
3
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 8 English

If the Earliest Due Date $$(EDD)$$ rule is used to sequence the jobs, the number of jobs delayed is

GATE ME 2010
4
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 7 English

Using the Shortest Processing Time $$(SPT)$$ rule, total tardiness is

GATE ME 2010
5
Six jobs arrived in a sequence as given below: GATE ME 2009 Industrial Engineering - Scheduling Question 9 English

Average flow time (in days) for the above jobs using Shortest Processing Time rule is

GATE ME 2009
6
A set of $$5$$ jobs is to be processed on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs. $$K$$ per day. GATE ME 2008 Industrial Engineering - Scheduling Question 10 English

A schedule that minimizes the total inventory cost is

GATE ME 2008
Marks 5
1
A job shop has $$6$$ orders to be completed by a single turning center. The processing times and due dates are as follows: GATE ME 1998 Industrial Engineering - Scheduling Question 3 English

Assume that all orders are ready for processing. Give a production schedule that minimizes the average flow time. Compare this schedule with one that minimizes tardiness (lateness).

GATE ME 1998
2
A job shop incurs a cost of Rs.$$60$$/- per day for each day a job is in the shop. At the beginning of a month there are five jobs in the shop with the following data: GATE ME 1996 Industrial Engineering - Scheduling Question 4 English

Which schedule will minimize the total cost?
What is the minimum total cost?
Which jobs (if any) fail to meet their due dates?

GATE ME 1996
3
Service workshop has four jobs on hand to be processed. The date and processing time for each of the jobs are given below GATE ME 1990 Industrial Engineering - Scheduling Question 5 English

Considering mean lateness and mean flow time, evaluate the shortest-time rule and least-slack rule and recommend the desirable rule.

GATE ME 1990
© 2025 ExamGOAL. All rights reserved.