Six jobs arrived in a sequence as given below:

Average flow time (in days) for the above jobs using Shortest Processing Time rule is
2
GATE ME 2008
MCQ (Single Correct Answer)
+2
-0.6
A set of $$5$$ jobs is to be processed on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs. $$K$$ per day.

A schedule that minimizes the total inventory cost is