Parts P1 - P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is _______ hours.
Part |
Milling (hours) |
Polishing (hours) |
P1 |
8 |
6 |
P2 |
3 |
2 |
P3 |
3 |
4 |
P4 |
4 |
6 |
P5 |
5 |
7 |
P6 |
6 |
4 |
P7 |
2 |
1 |
2
GATE ME 2017 Set 1
Numerical
+2
-0
Following data refers to the jobs $$(P, Q, R, S)$$ which have arrived at a machine for scheduling. The shortest possible average flow time is ___________ days.

Your input ____
3
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table.

If the Earliest Due Date $$(EDD)$$ rule is used to sequence the jobs, the number of jobs delayed is
4
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table.

Using the Shortest Processing Time $$(SPT)$$ rule, total tardiness is
Questions Asked from Marks 2
GATE ME Subjects
Engineering Mechanics
Machine Design
Strength of Materials
Heat Transfer
Production Engineering
Industrial Engineering
Turbo Machinery
Theory of Machines
Engineering Mathematics
Fluid Mechanics
Thermodynamics
General Aptitude