1
GATE ME 2022 Set 2
MCQ (Single Correct Answer)
+2
-0.66

Parts P1 - P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is _______ hours.

Part

Milling (hours)

Polishing (hours)

P1

8

6

P2

3

2

P3

3

4

P4

4

6

P5

5

7

P6

6

4

P7

2

1

A
31
B
33
C
30
D
32
2
GATE ME 2017 Set 1
Numerical
+2
-0
Following data refers to the jobs $$(P, Q, R, S)$$ which have arrived at a machine for scheduling. The shortest possible average flow time is ___________ days. GATE ME 2017 Set 1 Industrial Engineering - Scheduling Question 6 English
Your input ____
3
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 8 English

If the Earliest Due Date $$(EDD)$$ rule is used to sequence the jobs, the number of jobs delayed is

A
$$1$$
B
$$2$$
C
$$3$$
D
$$4$$
4
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 7 English

Using the Shortest Processing Time $$(SPT)$$ rule, total tardiness is

A
$$0$$
B
$$2$$
C
$$6$$
D
$$8$$
GATE ME Subjects
Engineering Mechanics
Machine Design
Strength of Materials
Heat Transfer
Production Engineering
Industrial Engineering
Turbo Machinery
Theory of Machines
Engineering Mathematics
Fluid Mechanics
Thermodynamics
General Aptitude