Following data refers to the jobs $$(P, Q, R, S)$$ which have arrived at a machine for scheduling. The shortest possible average flow time is ___________ days.

Your input ____
2
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table.

If the Earliest Due Date $$(EDD)$$ rule is used to sequence the jobs, the number of jobs delayed is
3
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table.

Using the Shortest Processing Time $$(SPT)$$ rule, total tardiness is
4
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Six jobs arrived in a sequence as given below:

Average flow time (in days) for the above jobs using Shortest Processing Time rule is
Questions Asked from Marks 2
GATE ME Subjects
Engineering Mechanics
Machine Design
Strength of Materials
Heat Transfer
Production Engineering
Industrial Engineering
Turbo Machinery
Theory of Machines
Engineering Mathematics
Fluid Mechanics
Thermodynamics
General Aptitude