GATE ME 2005
MCQ (Single Correct Answer)
+2
-0.6
A mould has a downsprue whose length is $$20$$ $$cm$$ and the cross sectional area at the base of the down sprue is $$1\,\,c{m^2}.$$ The down sprue feeds a horizontal runner leading into the mould cavity of volume $$1000\,\,c{m^3}.$$ The time required to fill the mould cavity will be
A
$$4.05$$ s
B
$$5.05$$ s
C
$$6.05$$ s
D
$$7.25$$ s
2
GATE ME 2004
MCQ (Single Correct Answer)
+2
-0.6
Gray cast iron blocks $$200 \times 100 \times 10\,\,mm$$ are to be cast in sand moulds. Shrinkage allowance for pattern making is $$1$$%. The ratio of the volume of pattern to that of the casting will be
A
$$0.97$$
B
$$0.99$$
C
$$1.01$$
D
$$1.03$$
3
GATE ME 2003
MCQ (Single Correct Answer)
+2
-0.6
With a solidification factor of $$0.97 \times {10^6}s/{m^2},$$ the solidification time (in seconds) for a spherical casting of $$200$$ $$mm$$ diameter is
A
$$539$$
B
$$1078$$
C
$$4311$$
D
None
4
GATE ME 1998
Subjective
+2
-0
Match the following GATE ME 1998 Production Engineering - Casting Question 42 English
GATE ME Subjects
Engineering Mechanics
Machine Design
Strength of Materials
Heat Transfer
Production Engineering
Industrial Engineering
Turbo Machinery
Theory of Machines
Engineering Mathematics
Fluid Mechanics
Thermodynamics
General Aptitude