Industrial Engineering
Line Balancing
Marks 21
GATE ME 2003
MCQ (Single Correct Answer)
+2
-0.6
A manufacturer produces two types of products, $$1$$ and $$2,$$ at production levels of $${x_1}$$ and $${x_2}$$ respectively. The profit is given is$$2{x_1} + 5{x_2}.$$ The production constraints are
$$$\eqalign{
& {x_1} + 3{x_2} \le 40 \cr
& 3{x_1} + {x_2} \le 24 \cr
& {x_1} + {x_2} \le 10 \cr
& {x_1} > 0,\,{x_2} > 0 \cr} $$$
The maximum profit which can meet the constraints is