Industrial Engineering
Production Planning and Control
Marks 1Marks 2Marks 5
Line Balancing
Marks 2
Forecasting
Marks 1Marks 2
Linear Programming
Marks 1Marks 2Marks 5
Assignment
Marks 1Marks 2
Inventory Control
Marks 1Marks 2Marks 5
Transportation
Marks 1Marks 2Marks 5
1
GATE ME 2022 Set 2
Numerical
+2
-0

A project consists of five activities (A, B, C, D and E). The duration of each activity follows beta distribution. The three time estimates (in weeks) of each activity and immediate predecessor(s) are listed in the table. The expected time of the project completion is ______ weeks (in integer).

Activity

Time estimates (in weeks)

Immediate predecessor(s)

Optimistic time

Most likely time

Pessimistic time

A

4

5

6

None

B

1

3

5

A

C

1

2

3

A

D

2

4

6

C

E

3

4

5

B, D

Your input ____
2
GATE ME 2022 Set 1
MCQ (Single Correct Answer)
+2
-0.66

Activities A to K are required to complete a project. The time estimates and the immediate predecessors of these activities are given in the table. If the project is to be completed in the minimum possible time, the latest finish time for the activity G is ______ hours.

$$ \begin{array}{|c|c|c|} \hline \text { Activity } & \text { Time (hours) } & \text { Immediate predecessors } \\ \hline \text { A } & 2 & - \\ \hline \text { B } & 3 & - \\ \hline \text { C } & 2 & - \\ \hline \text { D } & 4 & \text { A } \\ \hline \text { E } & 5 & \text { B } \\ \hline \text { F } & 4 & \text { B } \\ \hline \text { G } & 3 & \text { C } \\ \hline \text { H } & 10 & \text { D, E } \\ \hline \text { I } & 5 & \text { F } \\ \hline \text { J } & 8 & \text { G } \\ \hline \text { K } & 3 & \text { H, I, J } \\ \hline \end{array} $$
A
5
B
10
C
8
D
9
3
GATE ME 2017 Set 2
Numerical
+2
-0
A project starts with activity $$A$$ and ends with activity $$F.$$ The precedence relation and durations of the activities are as per the following table: GATE ME 2017 Set 2 Industrial Engineering - Pert and Cpm Question 9 English

The minimum project completion time (in days) is ___________

Your input ____
4
GATE ME 2016 Set 2
Numerical
+2
-0
A project consists of $$14$$ activities, $$A$$ to $$N$$. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node $$10$$ is _____________ GATE ME 2016 Set 2 Industrial Engineering - Pert and Cpm Question 10 English
Your input ____
GATE ME Subjects
Engineering Mechanics
Machine Design
Strength of Materials
Heat Transfer
Production Engineering
Industrial Engineering
Turbo Machinery
Theory of Machines
Engineering Mathematics
Fluid Mechanics
Thermodynamics
General Aptitude