1
GATE ME 2005
MCQ (Single Correct Answer)
+2
-0.6
A project has six activities $$(A$$ to $$F)$$ with respective activity durations $$7,5,6,6,8,4$$ days. The network has three paths $$A-B,C-D$$ and $$E-F.$$ All the activities can be crashed with the same crash cost per day. The number of activities that need to be crashed to reduce the project duration by $$1$$ day is
A
$$1$$
B
$$2$$
C
$$3$$
D
$$6$$
2
GATE ME 2003
MCQ (Single Correct Answer)
+2
-0.6
A project consists of activities $$A$$ to $$M$$ shown in the net in the following figure with the duration of the activities marked in days.

The project can be completed

A
between $$18,$$ $$19$$ day
B
between $$20, 22$$ days
C
between $$24, 26$$ days
D
between $$60, 70$$ days
3
GATE ME 2002
MCQ (Single Correct Answer)
+2
-0.6
A project consists of three parallel paths with mean durations and variances of $$(10,4), (12,4)$$ and $$(12,9)$$ respectively. According to the standard $$PERT$$ assumptions, the distribution of the project duration is
A
Beta with mean $$10$$ and standard deviation $$2$$
B
Beta with mean $$12$$ and standard deviation $$2$$
C
Normal with mean $$10$$ and standard deviation $$3$$
D
Normal with mean $$12$$ and standard deviation $$3$$
4
GATE ME 1990
MCQ (Single Correct Answer)
+2
-0.6
In the construction of networks, dummy activities are introduced in order to :
A
Compute the slack on all events
B
Transfer resources, if necessary, during monitoring
C
Clearly designate a precedence relationship
D
Simplify the crashing plan
GATE ME Subjects
Engineering Mechanics
Machine Design
Strength of Materials
Heat Transfer
Production Engineering
Industrial Engineering
Turbo Machinery
Theory of Machines
Engineering Mathematics
Fluid Mechanics
Thermodynamics
General Aptitude