Industrial Engineering
Production Planning and Control
Marks 1Marks 2Marks 5
Line Balancing
Marks 2
Forecasting
Marks 1Marks 2
Linear Programming
Marks 1Marks 2Marks 5
Assignment
Marks 1Marks 2
Inventory Control
Marks 1Marks 2Marks 5
Transportation
Marks 1Marks 2Marks 5
1
GATE ME 2016 Set 3
MCQ (Single Correct Answer)
+1
-0.3
In $$PERT$$ chart, the activity time distribution is
A
Normal
B
Binomial
C
Poisson
D
Beta
2
GATE ME 2014
MCQ (Single Correct Answer)
+1
-0.3
A minimal spanning tree in network flow models involves
A
all the nodes with cycle/loop allowed
B
all the nodes with cycle/loop not allowed
C
shortest path between start and end nodes
D
all the nodes with directed arcs
3
GATE ME 2009
MCQ (Single Correct Answer)
+1
-0.3
The expected time $$\left( {{t_e}} \right)$$ of a $$PERT$$ activity in terms of optimistic time $$\left( {{t_0}} \right)$$, pessimistic $$\left( {{t_p}} \right)$$ and most likely time $$\left( {{t_L}} \right)$$ is given by
A
$${t_e} = {{{t_0} + 4{t_L} + {t_P}} \over 6}$$
B
$${t_e} = {{{t_0} + 4{t_P} + {t_L}} \over 6}$$
C
$${t_e} = {{{t_0} + 4{t_L} + {t_P}} \over 3}$$
D
$${t_e} = {{{t_0} + 4{t_P} + {t_L}} \over 3}$$
4
GATE ME 2004
MCQ (Single Correct Answer)
+1
-0.3
In $$PERT$$ analysis a critical activity has
A
maximum Float
B
zero Float
C
maximum Cost
D
minimum Cost
GATE ME Subjects
Engineering Mechanics
Machine Design
Strength of Materials
Heat Transfer
Production Engineering
Industrial Engineering
Turbo Machinery
Theory of Machines
Engineering Mathematics
Fluid Mechanics
Thermodynamics
General Aptitude