ExamSIDE
Questions (Powered by ExamGOAL)
Joint Entrance Examination
Medical
Graduate Aptitude Test in Engineering
Civil Services
Defence
Staff Selection Commission
CBSE
Industrial Engineering
Queuing
Marks 1
Marks 2
Marks 5
Production Planning and Control
Marks 1
Marks 2
Marks 5
Line Balancing
Marks 2
Forecasting
Marks 1
Marks 2
Linear Programming
Marks 1
Marks 2
Marks 5
Assignment
Marks 1
Marks 2
Pert and Cpm
Marks 1
Marks 2
Marks 5
Inventory Control
Marks 1
Marks 2
Marks 5
Transportation
Marks 1
Marks 2
Marks 5
Scheduling
Marks 1
Marks 2
Marks 5
Previous
1
GATE ME 1996
MCQ (Single Correct Answer)
+2
-0.6
In an assembly line for assembling toys, five workers are assigned tasks which take times of $$10, 8, 6, 9$$ and $$10$$ minutes respectively. The balance delay for the line is
A
$$43.3\% $$
B
$$14.8\% $$
C
$$14.0\% $$
D
$$16.3\% $$
Check Answer
Previous
Questions Asked from Marks 2
GATE ME 2006 (1)
GATE ME 2004 (1)
GATE ME 1996 (1)
GATE ME Subjects
Engineering Mechanics
Machine Design
Strength of Materials
Heat Transfer
Production Engineering
Industrial Engineering
Turbo Machinery
Theory of Machines
Engineering Mathematics
Fluid Mechanics
Thermodynamics
General Aptitude