A project with the following data is to be implemented:

(a) What is the minimum duration of the project?
(b) Draw a Gantt chart for the early schedule
(c) Determine the peak requirement of money and the day on which it occurs in above schedule.
2
GATE ME 1993
Subjective
+5
-0
For a small project with five jobs, the following data is given
(i) Draw the project network in activity on arc mode
(ii) Under $$PERT$$ assumptions, determine the distribution of project duration.

(i) Draw the project network in activity on arc mode
(ii) Under $$PERT$$ assumptions, determine the distribution of project duration.