Quantitative Aptitude
Computation of whole numbers
MCQ (Single Correct Answer)
Relationships between Numbers
MCQ (Single Correct Answer)
Mixture and Alligation
MCQ (Single Correct Answer)
Ratio & Proportion
MCQ (Single Correct Answer)
Basic Algebraic Identities of School Algebra & Elementary Surds
MCQ (Single Correct Answer)
Triangle and Its Various Kinds of Centres
MCQ (Single Correct Answer)
Congruence and Similarity of Triangles
MCQ (Single Correct Answer)
Right Circular Cone
MCQ (Single Correct Answer)
Right Circular Cylinder
MCQ (Single Correct Answer)
Height and Distance
MCQ (Single Correct Answer)
Bar Chart & Pie chart
MCQ (Single Correct Answer)
Rectangular Parallelepiped
MCQ (Single Correct Answer)
Trigonometric Ratio
MCQ (Single Correct Answer)
Standard Identities
MCQ (Single Correct Answer)
Complementary Angles
MCQ (Single Correct Answer)
1
SSC CGL Tier I - 27th July 2023 Shift 2
MCQ (Single Correct Answer)
+2
-0.5
P, Q and R can complete a piece of work in 9, 12 and 18 days, respectively. Working together, how much work can they complete in one day?
1
$\frac{2}{3}$
2
$\frac{1}{2}$
3
$\frac{1}{3}$
4
$\frac{1}{4}$
2
SSC CGL Tier I - 27th July 2023 Shift 2
MCQ (Single Correct Answer)
+2
-0.5
Ram and Ramesh can do a work in 12 days, Ramesh and Somesh in 15 days and Somesh and Ram in 10 days. If Ram, Ramesh and Somesh work together, in how many days will they complete the work?
1
10
2
8
3
12
4
6
3
SSC CGL Tier I - 27th July 2023 Shift 2
MCQ (Single Correct Answer)
+2
-0.5
A, B and C can do a piece of work in 20, 30 and 60 days, respectively. In how many days can A do the work if he is assisted by both B and C on every third day?
1
10
2
15
3
12
4
18
4
SSC CGL Tier I - 27th July 2023 Shift 2
MCQ (Single Correct Answer)
+2
-0.5
Benny can do a piece of work in 24 days. Chethan and David can do the same work individually in 36 and 48 days, respectively. All of them begin the work together. However, Benny leaves the work 4 days before the completion of work and Chethan leaves the work 10 days before the completion of the work. David worked till the end and completed the work. Find the number of days in which the work was completed.
1
16
2
20
3
18
4
15