1
GATE CE 2024 Set 2
Numerical
+2
-0
The table shows the activities and their durations and dependencies in a project.
Activity | Duration (Days) | Depends on |
---|---|---|
A | 8 | - |
B | 4 | A |
C | 4 | B |
D | 4 | C, L |
F | 4 | A |
G | 4 | F |
H | 6 | G, L |
K | 10 | A |
L | 6 | F, K |
The total duration (in days) of the project is __________ (in integer).
Your input ____
2
GATE CE 2022 Set 2
Numerical
+2
-0
The activities of a project are given in the following table along with their durations and dependency.
Activities | Duration (day) | Depends on |
---|---|---|
A | 10 | - |
B | 12 | - |
C | 15 | A |
D | 14 | B |
E | 10 | B, C |
The total float of the activity E (in day) is _________. (in integer)
Your input ____
3
GATE CE 2017 Set 1
Numerical
+2
-0
The activity details of a project are given below:
The estimated minimum time (in days) for the completion of the project will be________

Your input ____
4
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+2
-0.6
The activity-on-arrow network of activities for a construction project is shown in the figure.
The durations (expressed in days) of the activities are mentioned below the arrows.
The critical duration for this construction project is

Questions Asked from Marks 2
GATE CE Subjects
Engineering Mechanics
Strength of Materials Or Solid Mechanics
Structural Analysis
Construction Material and Management
Reinforced Cement Concrete
Steel Structures
Geotechnical Engineering
Fluid Mechanics and Hydraulic Machines
Hydrology
Irrigation
Geomatics Engineering Or Surveying
Environmental Engineering
Transportation Engineering
Engineering Mathematics
General Aptitude