1
GATE CE 2022 Set 1
MCQ (Single Correct Answer)
+1
-0.33
The project activities are given in the following table along with the duration and dependency.
Activities | Duration (days) | Depends on |
---|---|---|
P | 10 | - |
Q | 12 | - |
R | 5 | P |
S | 10 | Q |
T | 10 | P, Q |
Which one of the following combinations is correct?
2
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+1
-0.3
A construction project consists of twelve activities. The estimated duration (in days) required
to complete each of the activities along with the corresponding network diagram is shown
below.
Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,

Questions Asked from Marks 1
GATE CE Subjects
Engineering Mechanics
Strength of Materials Or Solid Mechanics
Structural Analysis
Construction Material and Management
Reinforced Cement Concrete
Steel Structures
Geotechnical Engineering
Fluid Mechanics and Hydraulic Machines
Hydrology
Irrigation
Geomatics Engineering Or Surveying
Environmental Engineering
Transportation Engineering
Engineering Mathematics
General Aptitude