GATE CE 2024 Set 2
MCQ (Single Correct Answer)
+1
-0.33
Consider the following data for a project of 300 days duration.
Budgeted Cost of Work Scheduled (BCWS) = Rs. 200
Budgeted Cost of Work Performed (BCWP) = Rs. 150
Actual Cost of Work Performed (ACWP) = Rs. 190
The ‘schedule variance’ for the project is
2
GATE CE 2024 Set 1
MCQ (Single Correct Answer)
+1
-0.33
Consider the statements P and Q.
P: Client’s Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.
Q: Client’s Detailed Estimate is used for controlling costs during the execution of the project.
Which one of the following options is CORRECT?
3
GATE CE 2017 Set 2
Numerical
+1
-0
For a construction project. The mean and standard deviation of the completion time are 200
days and 6.1 days, respectively. Assume normal distribution and use the value of standard
normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days)
for the completion of the project would be __________.
Your input ____
Questions Asked from Marks 1
GATE CE Subjects
Engineering Mechanics
Strength of Materials Or Solid Mechanics
Structural Analysis
Construction Material and Management
Reinforced Cement Concrete
Steel Structures
Geotechnical Engineering
Fluid Mechanics and Hydraulic Machines
Hydrology
Irrigation
Geomatics Engineering Or Surveying
Environmental Engineering
Transportation Engineering
Engineering Mathematics
General Aptitude