Consider the following statements:
P. Walls of one brick thick are measured in square meters.
Q. Walls of one brick thick are measured in cubic meters.
R. No deduction in the brickwork quantity is made for openings in walls up to 0.1 $$m^2$$ area.
S. For the measurement of excavation from the borrow pit in a fairly uniform ground, dead men are left at suitable intervals.
For the above statements, the correct option is
A
P-False; Q-True; R- False: S-True
B
P-False; Q-True: R-False; S-False
C
P-True; Q-False; R-True; S- False
D
P-True; Q-False; R-True; S-True
GATE CE Subjects
Engineering Mechanics
Strength of Materials Or Solid Mechanics
Structural Analysis
Construction Material and Management
Reinforced Cement Concrete
Steel Structures
Geotechnical Engineering
Fluid Mechanics and Hydraulic Machines
Hydrology
Irrigation
Geomatics Engineering Or Surveying
Environmental Engineering
Transportation Engineering
Engineering Mathematics
General Aptitude