Marks 1
1
A line balancing problem is solved in the context of
GATE PI 2015
Marks 2
1
A manufacturing line requires $$7.2$$ minutes to make a product. The line has six workstations arranged as per the required sequence of operations. Total production required is $$300$$ products in $$7.5$$ hours. At steady state, the line efficiency, in $$\% $$, is ______________
GATE PI 2015