LevellingTraversingTheodolites and Plane Table SurveyingMeasurement of Area, Volume and Theory of Errors and Survey AdjustmentCurvesField Astronomy and Photogrammetric SurveyingBasics of GIS, GPS and Remote SensingAngular Measurements and Compass SurveyBasic ConceptsLinear Measurements and Chain SurveyLinear Measurements and Chain Survey
Practice QuestionsMarks 1
1
The length of a baseline measured on ground at an elevation of 300m above mean sea level is 2250 m. The required correction to reduce to sea level length. (given the radius of earth is 6370km) is _______.
GATE CE 1991
2
The required slope correction for a length of 60m, along a gradient of 1 in 20 is
GATE CE 1990