LevellingTraversingTheodolites and Plane Table SurveyingMeasurement of Area, Volume and Theory of Errors and Survey AdjustmentCurvesField Astronomy and Photogrammetric SurveyingBasics of GIS, GPS and Remote SensingAngular Measurements and Compass SurveyBasic ConceptsLinear Measurements and Chain Survey
Levelling
Practice Questions
Marks 1
1
If the horizontal distance between a staff point and the point of observation is $d$, the error due to the curvature of earth is proportional to
GATE CE 2025 Set 1
Marks 2
1

In levelling between two points A and B on the opposite banks of a river, the readings are taken by setting the instrument both at $A$ and $B$, as shown in the table. If the $R L$ of $A$ is 150.000 m , the $R L$ of $B$ (in m ) is __________ (rounded off to 3 decimal places).

Level position Staff readings
A B
A 1.800 1.350
B 1.450 0.950
GATE CE 2025 Set 1
2

Trigonometric levelling was carried out from two stations P and Q to find the reduced level (R. L.) of the top of hillock, as shown in the table. The distance between Stations P and Q is 55 m. Assume Stations P and Q, and the hillock are in the same vertical plane. The R. L. of the top of the hillock (in m) is ____________ (round off to three decimal places).

$$ \begin{array}{|c|c|c|c|} \hline \text { Station } & \begin{array}{c} \text { Vertical } \\ \text { angle of } \\ \text { the top of } \\ \text { hillock } \end{array} & \begin{array}{c} \text { Staff } \\ \text { reading on } \\ \text { benchmark } \end{array} & \begin{array}{c} \text { R.L. of } \\ \text { bench } \\ \text { mark } \end{array} \\ \hline \mathrm{P} & 18^{\circ} 45^{\prime} & 2.340 \mathrm{~m} & \begin{array}{c} 100.000 \\ \mathrm{~m} \end{array} \\ \hline \mathrm{Q} & 12^{\circ} 45^{\prime} & 1.660 \mathrm{~m} & \\ \hline \end{array} $$
GATE CE 2023 Set 1