Construction Material and Management
Critical Path Method
Marks 1Marks 2
Construction Materials
Marks 1Marks 2
Program Evolution Review Technique
Marks 1Marks 2
1
GATE CE 2025 Set 1
MCQ (More than One Correct Answer)
+2
-0

In the context of construction project management, which of the following statements is/are true:

A
A dummy activity will consume time and resources
B
The programme evaluation and review technique (PERT) is best suited for projects with large uncertainties in the duration of activities
C
A Gantt chart is commonly used for identifying the 'critical path' of activities in a project
D
Free float is the amount of time by which the start of an activity can be delayed without causing a delay in the start of a following activity
2
GATE CE 2016 Set 1
Numerical
+2
-0
The Optimistic Time (O), most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P. GATE CE 2016 Set 1 Construction Material and Management - Program Evolution Review Technique Question 4 English The expected completion time (in days) of the project is _______.
Your input ____
GATE CE Subjects
Engineering Mechanics
Strength of Materials Or Solid Mechanics
Structural Analysis
Construction Material and Management
Reinforced Cement Concrete
Steel Structures
Geotechnical Engineering
Fluid Mechanics and Hydraulic Machines
Hydrology
Irrigation
Geomatics Engineering Or Surveying
Environmental Engineering
Transportation Engineering
Engineering Mathematics
General Aptitude